Growth fuelling Waipa water spend

Stormwater. pexels.com

Waipa District Council says it will need to spend around $62 million on stormwater infrastructure to open up new areas for development in Cambridge.

Waipa District Council is looking down the barrel of an extra $100-plus million spend on water services over the coming decade.

And while most of that money will be returned to the Council by land developers and others, there are concerns the wider infrastructure industry may not have the capacity to get the work done.

In its 2015-2025 10-Year Plan, Council budgeted close to $220 million for water, wastewater and stormwater work.  That work is now underway, including an upgrade of the Karapiro water treatment plant and plans to upgrade the Te Awamutu water supply.

But massive growth, particularly in Cambridge, means Waipa ratepayers will need to finance huge, new infrastructure projects to allow housing areas to develop in time for projected demand.

Waipa District Council’s service delivery group manager Barry Bergin

Group manager service delivery Barry Bergin said much of the proposed new spend – around $62 million – was ring-fenced for stormwater infrastructure in Cambridge west.

By 2050 a further 14,000 people will call Cambridge home, driving demand for an estimated 212 new houses each year. Much of the new development will be on flat land where soakage is poor.

In addition to new Cambridge housing areas, around $22 million will also be needed to provide water, wastewater and stormwater to the Hautapu industrial site.  Road upgrades are needed to open up the site and provide connections to the Cambridge section of the Waikato Expressway.

Bergin said massive growth in the district was stretching his team’s ability to deliver the capital projects but Waipa was not alone. Across New Zealand, councils were struggling to attract specialist water and technical staff.  Many professional consulting firms, used to support council staff, were already at capacity, he said.

“We already have an enormous capital works programme in front of us and growth across the district is adding to that challenge. It’s a very positive challenge to have but we will need to think very carefully about priorities and funding.”

“Those will be issues that elected members, as the decision-makers, will need to weigh up when they consider options for the 10-Year Plan.”

Councillors have yet to discuss the potential capital works programme in detail.

Those discussions will be held soon before a first-cut of the 2018-2028 draft 10-Year Plan is developed prior to Christmas.

More Recent News

Tour and a history lesson

A polished black granite monument erected in memory of Patrick Corboy, a former Waipā County chairman, featured in a Hamilton West cemetery tour undertaken by historian Lyn Williams last month. Corboy, who died in 1900…

Watch those power poles

Police are joining Waipā Networks in urging drivers to take extra care following a sharp rise in crashes involving power poles. The electricity distribution company’s crews responded to 40 vehicle-versus-pole incidents in 2025, 12 more…

Treasuring Tom Roa

Two children were in toilet cubicles at a new preschool where Māori was being taught. One called to the other ko mutu koe? (have you finished?). The response came “ae, ko mutu koe” (yes). To…

Celebrating the champions …

Two Cambridge identities made the 2026 New Year’s Honours List – Judith Hamilton becomes an officer of the New Zealand Order of Merit (ONZM) for her services to rowing and Kevin Burgess a Member of…